Wind power in Croatia has been growing since the first wind farm was installed in the country in 2004.[1] During 2021, the energy produced from wind farms amounted to 1,904 GWh.[2] The total wind power grid-connected capacity in Croatia was 1,043 MW as of 2022.[3]

History

The first wind farm was installed on the island of Pag in 2004.[1] In 2006 another farm opened near Šibenik. On July 1, 2007 the Croatian Government enacted five bylaws on incentives to electricity generation from renewable resources, including feed-in tariffs.[4]

Currently in Croatia there's a total of 364 wind turbines which generate total of 970.15 MW or electric energy, but with new turbines coming on-line all the time, it is expected that by mid 2020s total installed power will reach 3,200 MW,[5] As of early 2020 Croatia generates around 28.3% renewable energy, Government hopes Croatia could generate around 37.5% renewable energy from wind and solar by 2030 and has adopted new strategy to achieve that target.[6] By the end of 2021 renewable energy in Croatia is expected to generate around 1060 MW from Wind and Solar alone or around 32% of all energy consumption from renewable energy source, Croatia exceeded EU's renewable energy targets and exceed that by a wide margin. In 2020 country generated 28.3% of all its energy from the renewable sources of energy, installed capacity at the end of 2020 includes 89 MW Solar farms[7] and these are set to double in 2021 to 184 MW installed capacity,[8] 803.1 MW Wind farm are set to increase to at least 875 MW by end of 2021, and other sources such as biomass and other sources will exceed 2020 figure of total 3,226 MW installed renewable energy generation by significant margin.[9][10] At present rate of growth and planned investments over next 5-7 year period, energy generated from Wind and solar should easily reach 40% of total energy consumption in Croatia with 50% highly probable, achieving targets set by Germany, Sweden, Norway, Denmark, Finland and Austria. Although Croatian Government has set modest targets in terms of renewable energy share of total energy consumption, initially 20% by 2020 and now modest 37.5% by 2030 or 54% by 2050, the country is rapidly approaching targets set for 2050, at current rate of expansion of renewable sources in Croatia, it is quite possible by 2035 Croatia will meet its 2050 targets, some 15 years ahead.

List of wind farms

Wind farm Production capacity
(MW)
Annual
production
(GWh)
Wind turbines Year of commissioning Source
VE Senj15653039 x Shanghai Electric – 4.0 MW2021[11]
VE Krš-Pađene14248048 x Nordex2021
VE Korlat5817018 x Nordex – 3.2 MW2021[12]
VE Lukovac481107 x GE Energy – 2.85 MW
9 x GE Energy – 3.2 MW
2017[13]
VE Poštak44.210013 × Siemens – 3.4 MW2017[14]
VE Danilo43.710019 × Enercon – 2.3 MW2014[15]
VE Vrataruša4212514 × Vestas – 3 MW2010[16]
VE Zelengrad4211014 × Vestas – 3 MW2014[17]
VE Ogorje4210014 × Vestas – 3 MW2015[18]
VE Kamensko-Voštane4011414 × Siemens – 3 MW2013[19]
VE Bruška36.812216 × Siemens – 2.3 MW2011[20]
VE Ponikve36.812216 × Enercon – 2.3 MW2012[21]
VE Rudine34.28512 × GE Energy – 2.85 MW2015[22]
VE Katuni34.29512 × GE Energy – 2.85 MW2016[23]
VE Ljubač32.4969 x Nordex – 3.6 MW2022[24]
VE Jelinak308120 × Acciona – 1.5 MW2013[25]
VE Glunča20.7539 x Enercon – 2.3 MW2016[26]
VE Pometeno brdo205015 × Končar – 1 MW
2 × Končar – 2.5 MW
2015[27]
VE Jasenice11.5445 x Enercon – 2.3 MW2020[28]
VE Trtar-Krtolin11.22814 × Enercon – 0.8 MW2007[29]
VE Crno brdo10.5277 × Leitwind – 1.5 MW2011[30]
VE Orlice9.6253 x Enercon – 0.8 MW
8 x Enercon – 0.9 MW
2009[31]
VE Velika Popina9.2264 × Siemens – 2.3 MW2011[32]
VE Zadar 49.2304 × Siemens – 2.3 MW2013[33]
VE Ravne 15.95157 × Vestas – 0.85 MW2004[34]
In total970.152,8383642004–2022

See also

References

  1. 1 2 "Supply: Energy Sources". Archived from the original on 2019-03-23. Retrieved 2008-11-01.
  2. Ivanković, Igor (2022). "Godišnje izvješće 2021" [Annual report 2021] (PDF). HOPS (in Croatian). Zagreb: Hrvatski operator prijenosnog sustava. Retrieved 16 June 2022.
  3. "RENEWABLE CAPACITY STATISTICS 2023" (PDF). Retrieved 2023-10-07.
  4. Ognjan, Diana; Stanić, Zoran; Tomšić, Željko (13 March 2008). "Isplativost poticajne otkupne cijene za projekte vjetroelektrana u Republici Hrvatskoj" [Profitability of Incentive Purchase Prices for Wind farm Projects in Croatia]. Energija. Zagreb, Croatia. 57 (2): 178–199 via Hrčak.
  5. "Aktivne 204 elektrane koje koriste obnovljive izvore energije" [204 active power plants using renewable energy sources]. Večernji list (in Croatian). 4 May 2013. Retrieved 15 June 2022.
  6. "Government adopts national action plan for renewables". 2013-10-17. Archived from the original on 2013-12-21.
  7. "National Energy and Climate Plan Croatia". Archived from the original on 2021-05-22.
  8. "Product". WindEurope.
  9. "CROATIA RENEWABLE ENERGY". International Trade Administration. 23 March 2022. Retrieved 16 August 2022.
  10. Renewable capacity statistics 2021 (PDF). Abu Dhabi: International Renewable Energy Agency (IRENA). 2021. ISBN 978-92-9260-342-7.
  11. "VE Senj: ususret montaži vjetroagregata" [VE Senj: towards the installation of wind turbines]. energetika-net (in Croatian). 21 September 2020. Retrieved 24 November 2021.
  12. "U rad puštena Vjetroelektrana Korlat" [Korlat Wind Farm was put into operation]. HRT (in Croatian). 28 April 2021. Retrieved 26 October 2021.
  13. "Lukovac(Croatia)". The Wind Power. 26 October 2021. Retrieved 26 October 2021.
  14. Vjetroelektrana Poštak. Porzana. 16 March 2018. Archived from the original on 28 October 2021. Retrieved 17 April 2022 via YouTube.
  15. Jerkić, Leo (7 June 2014). "Službeno završeno testiranje pogona vjetroelektrane Danilo" [Officially completed testing of the Danilo wind farm]. vjetroelektrane.com (in Croatian). Retrieved 15 June 2022.
  16. Jerkić, Edo (8 April 2011). "Vjetroelektrana Vrataruša" [Wind farm Vrataruša]. vjetroelektane.com (in Croatian). Retrieved 16 June 2022.
  17. "Danas se otvara vjetroelektrana Zelengrad – Obrovac". www.vecernji.hr (in Croatian). Retrieved 2023-10-07.
  18. "Litvanska tvrtka kupila vjetropark u Ogorju i infrastrukturu za buduću gradnju kraj Zadra". www.direktno.hr (in Croatian). Archived from the original on 2018-09-29. Retrieved 2023-10-07.
  19. "U Trilju otvorena vjetroelektrana". www.poslovni.hr (in Croatian). Retrieved 2023-10-07.
  20. "Vjetroelektrana Bruška" [Wind farm Bruška]. vjetroelektrane.com (in Croatian). 3 April 2012. Retrieved 16 June 2022.
  21. Zelenko, Iva (23 May 2013). "Otvorena vjetroelektrana Ponikve" [Wind farm Ponikve opened]. vjetroelektrane.com (in Croatian). Retrieved 16 June 2022.
  22. Jerkić, Leo (29 April 2016). "Puštena u rad vjetroelektrana Rudine vrijedna 400 milijuna-kuna" [The Rudine wind farm worth HRK 400 million was put into operation]. vjetroelektrane.com (in Croatian). Retrieved 16 June 2022.
  23. "Web Server's Default Page". katuni.wpd-group.com.
  24. "VE Ljubač: Petrol otvorio svoj drugi vjetropark u Hrvatskoj" [WPP Ljubač: Petrol opened its second wind farm in Croatia]. Ekovjesnik (in Croatian). 10 May 2022. Retrieved 16 June 2022.
  25. "Vjetroelektrana Jelinak u probnom pogonu". www.vjetroelektrane.com (in Croatian). Retrieved 2023-10-07.
  26. "Projekti vjetroelektrana". www.tecoi.hr (in Croatian). Retrieved 2023-10-07.
  27. Zelenko, Iva (3 April 2012). "Dovršena prva faza izgradnje VE Pometeno brdo" [The first phase of construction of WPP Pometeno brdo has been completed]. vjetroelektrane.com (in Croatian). Retrieved 16 June 2022.
  28. Jasenice (Croatia) - Wind farms - Online access - The Wind Power pristupljeno 13. travnja 2021.
  29. Jerkić, Edo (28 March 2011). "Vjetroelektrana Trtar-Krtolin" [Wind farm Trtar-Krtolin]. vjetroelektrane.com (in Croatian). Retrieved 16 June 2022.
  30. Jerkić, Edo (13 September 2012). "Vjetroelektrana Crno Brdo" [Wind farm Crno Brdo]. vjetroelektrane.com (in Croatian). Retrieved 16 June 2022.
  31. Jerkić, Edo (1 April 2011). "Vjetroelektrana Orlice" [Wind farm Orlice]. vjetroelektrane.com (in Croatian). Retrieved 16 June 2022.
  32. Jerkić, Edo (25 November 2010). "Vjetroelektrana Velika Popina" [Wind farm Velika Popina]. vjetroelektrane.com (in Croatian). Retrieved 16 June 2022.
  33. "Eko Zadar Dva gradi vjetroelektranu u Bukovici". www.energetika-net.com (in Croatian). 2013-04-16. Retrieved 2023-10-07.
  34. Jerkić, Nives (7 December 2010). "Vjetroelektrana Ravne 1, Pag" [Wind farm Ravne 1, Pag]. vjetroelektrane.com (in Croatian). Retrieved 16 June 2022.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.