Third Menai Crossing
Preferred location of the crossing in 2018, before cancellation
LocationMenai Strait, Wales
Project websitegov.wales/a55-3rd-menai-crossing-0
StatusScrapped (2023), replaced with transport strategy review
TypeDual-carriageway road bridge
Cost estimate£400 million (2022)
Start datecancelled

The Third Menai Crossing (or (A55) 3rd Menai Crossing) was a proposed bridge over the Menai Strait, connecting the Isle of Anglesey with mainland Wales. The bridge was proposed to carry the A55 as a dual carriageway, and would have superseded the current A55 Britannia Bridge.

There were proposals for a tunnel in 2001, but were deemed implausible. The first proposals for a bridge were made in 2007 and with a preferred route for the bridge being selected in 2018.

The crossing was projected to cost £400 million and take seven years to build. While no exact bridge design had been confirmed, a third-party suggested it be held up by statues of Bendigeidfran.

In June 2021, the Welsh Government indefinitely paused the proposal's progress as part of a review of road building projects over concerns of climate change emissions. In December 2022, the government had set 2030 as a "likely" date for the bridge's completion but did not formally commit whether the project would go ahead.

On 14 February 2023, the Welsh Government announced the entire project would not go ahead, citing efforts to reduce car usage, its environmental impact and it being a "blot" on the landscape. The "Menai Corridor" public transport strategy review is to be set up to replace plans for the formerly proposed crossing, with recommendations to be presented by the North Wales Transport Commission by mid-2023.[1][2][3] Issues with financing the project was later stated by the government as another reason why the project could not proceed.[4] Lee Waters, deputy minister for climate change, later stated the crossing could be considered again as part of a wider review into the infrastructure of North Wales, rather than individually.[5] The review into North Wales' infrastructure did not support a third crossing, but recognised that there may be future reasons to consider it.

Background and history

There are currently two crossings over the Menai Strait, the Menai Suspension Bridge and Britannia Bridge, carrying the A5, and the A55 and North Wales Coast Line respectively. The A5 Menai Bridge is both height and width restrictive, whereas the Britannia Bridge is the only part of the 87-mile (140 km) A55 dual carriageway where it is a single carriageway (1 lane either way compared to 2 lanes on the rest of the route) and was originally only for rail traffic, until a rebuilding in the 20th century opening it for road traffic.[6][7][8][9][10]

In 2001, a tunnel was proposed to be built under the strait connecting a site near Gaerwen on Anglesey, and a site near Bangor, on the mainland. It was not considered due to its lack of plausibility as there was a geological fault present in the strait and the costs of a tunnel were excessive.[11]

A later solution proposed was to convert the Britannia Bridge into three-lanes, with one of the lanes alternating direction depending on rush-hour priority during the day. The proposal was unconvincing to road planners, who described the bridge as being too narrow and traffic approached the bridge at high speed. But the initial feasibility study had proved positive for a three-lane Britannia Bridge, and is continuously brought up as a short-term solution to relieve congestion on the crossings.[11]

In 2007, a public consultation on the crossings first proposed a third crossing,[8][12] and it presented four/five options to address traffic over the strait. The four options, (or five if including no new bridge as an option) were:

  • Build no new bridge, as either "do nothing"; or simply increase connectivity between A55 and A5 (to the Menai Bridge).
  • Widen existing Britannia Bridge
  • Build a new multi-span bridge east of the existing Britannia Bridge
  • Build a new long-span bridge east of the existing Britannia Bridge
  • Build a bridge to the west of the existing Britannia Bridge.[12]
The Britannia Bridge from the east on Anglesey, roughly on the proposed preferred route of the third crossing.

All options aside "do nothing", also involved improvements to A55 Junction 9 and 8A, and for some eastern bridges junction 8.[13]

During the public consultation the Welsh government stated its objectives for the proposed crossing. To improve journey times and journey reliability between A55 Junction 7 and 10, improve network resillience by providing an alternative bridge during maintenance and emergencies, improve accessibility for pedestrians and cyclists, and promote safer trips over the strait.[10][14] 70 per cent of the respondents to the consultation supported a new bridge.[11]

Following 2011 plans for a Wylfa Newydd nuclear power station on Anglesey, concerns over increased construction road traffic for the new power station on the two existing bridges were raised. With a third crossing called as a potential solution.[15] Plans for the power station were paused in 2019, potentially impacting the case for the crossing.[16]

In 2013, the Welsh Government announced the project would be back on their agenda.[17]

A Strategic Outline Business case by the Welsh Government backed the need for a crossing in 2016.[10] Plaid Cymru had welcomed the proposal in 2016, as a way to tackle traffic congestion in the area. Welsh Conservative MS, Russell George said such a project was "long overdue".[9] In October 2017, the Welsh Government and Plaid Cymru agreed in a draft budget to allocate £3 million to support the design and development of the third crossing.[18] The crossing was estimated to cost £135 million in December 2017.[7]

In October 2018, First Minister of Wales Carwyn Jones announced the preferred option. The option chose was described as the "purple route", involving a new bridge to be built to the east (but not directly next) of the existing Britannia Bridge, with facilities for pedestrians and cyclists. The purple option to the east garnered 25% of the first choice vote and total majority of respondents in a public consultation.[6][11][19] A bridge design was not selected at the time, a local engineer had proposed it be held by statues of Bendigeidfran.[11] Extending Garth Pier across the strait as a pedestrian and cyclist crossing was also proposed by a local, but deemed unrealistic.[11]

Construction was expected to start[6][9] and potentially open in 2021,[8] but was delayed due to the COVID-19 pandemic. In June 2021 following the 2021 Senedd election, the project was indefinitely shelved by Deputy Minister for Climate Change (with responsibility for Transport) Lee Waters, as part of a review of all proposed road construction projects in Wales and how to reduce carbon emissions over concerns of climate change.[20][21][22] A decision was expected to be made by November 2022, but delayed, with Waters stating cuts in the November 2022 United Kingdom autumn statement by Chancellor of the Exchequer, Jeremy Hunt as the reason for the delay.[23]

In December 2022, the Welsh Government announced that a new crossing starting construction by 2027, and be completed by 2029–30 was "likely", but the government had not formally committed to the project.[24][25][26] Waters however stated such a crossing would take seven years to build.[27] This announcement follows the temporary closure of the Menai Suspension Bridge from October 2022 to early 2023 for urgent safety repairs, causing severe congestion on the Britannia Bridge and the local area, and media reported this increased calls for a third crossing.[27][28][11]

Scrapping

On 14 February 2023, the project was announced it would not go ahead, as part of the Welsh Government roads review, over concerns of increasing car usage and therefore carbon emissions.[1]

Prior to scrapping the project, the government has spent £2 million on planning for the project.[29]

The roads review stated that the project should not go ahead due to efforts being made to reduce car usage would make a new bridge redundant and its major environmental impact. The review stated the construction of the purple route would cause "large" to "moderate" impacts on local protected SSSIs and SACs, as well as destroying ancient woodland and being "a blot on the existing landscape".[2][30]

Traffic models stated in the review showed a projected increase of traffic from 2017 to 2038 by 17% and 18% on the Britannia and Menai Suspension bridges respectively. However such models were performed before the Welsh Government announced its commitment to reduce car use, and its announcement of the North Wales Metro.[2][30]

The crossing is to be replaced by a review for a "Menai Corridor" public transport strategy, whose first recommendations are to be presented by the North Wales Transport Commission by mid-2023 on how to improve congestion and resilience of the existing bridges. The Daily Post raised wind shielding, new traffic controls and signage as potential alternative improvements.[1][2][31]

Lee Waters, deputy minister for Climate Change, justified the scrapping stating the review put the issue of climate change and meeting net zero at the centre of decision making, and they should not be "doing the same thing over and over", for Wales to meet the net zero target. Waters stated new roads are still being built, although they must meet stricter criteria, and that they are investing in alternative non-road transport projects.[32][33] Waters also admitted the government may not have the finances to fund all the projects, and criticised the UK Government's lack of investment in infrastructure.[31] Waters stated that due to the Welsh Government's lack of funds, various projects would "not be happening any time soon [...] [The Welsh Government] haven't got the money".[4] In another statement, Waters said a third crossing could be considered as part of a wider review of the infrastructure of North Wales by the Burns Commission, and that there is a need to be "pragmatic" rather than "be[ing] dogmatic about [the crossing]".[5]

Post-scrapping

A campaign group "Britain Remade" started organising support for a new crossing, grouping supporters of the scheme such as Virginia Crosbie, Conservative MP for Ynys Môn, and local Plaid Cymru councillors. Polling done by the group claimed the government's scrapping of the project was opposed by 46% of those polled residing in North Wales, compared to 33% supporting the scrapping who were also located in North Wales.[34][35] In November 2023, the group launched a petition for a third crossing, and argued that constructing new roads can be done alongside efforts to tackle climate change, with the group's research claiming that the impact 370 miles of new UK roads had a minimal increase in carbon emissions, and that new roads increase the appeal for electric cars.[35][36]

In December 2023, the North Wales Transport Commission, set up following the roads review, and led by former permanent secretary to the UK Treasury Terry Burns, revealed its sixteen recommendations for the Menai Strait crossings. The commission's recommendations ranged from installing wind deflectors on the Britannia Bridge, reconfiguring junctions, introduce park-and-rides, increase train frequency, ban overtaking on the Menai Suspension Bridge, as well as lowering the speed limit and implementing camera enforcement on the Britannia Bridge. It proposed a study into a three-lane tidal system at peak traffic times but does question whether there would be any benefits with such due to the investment needed and ongoing costs of a scheme. The commission recognised calls to introduce road tolling on the bridges but did not recommend it. The commission did not list a third crossing among its recommendations although stated that they recognise that there may be some reasons to consider it in the future, such as the status of Wylfa Newydd nuclear power station.[37]

Proposed location

Three potential locations were considered in 2017, all around the Britannia Bridge. A 'red option' west of the Britannia Bridge, an 'orange option' directly to the east, or a 'purple option' further to the east of the Britannia Bridge, with the latter, later chosen. All options minimally involved improvements to the A55 junction 9 and 8A.[13]

The preferred proposed location for the crossing, selected from a set of four options in October 2018, was situated east (but not directly next) of the existing Britannia Bridge. The location was within a Special Landscape and Marine Character Area, as well as the Anglesey AONB.[6][19][38][39]

Alternative location

When the scrapping of the project project was announced in February 2023, it was revealed an alternative "Sienna" option was considered by planners, as well as reserving land for the orange route as a backup. The Sienna option would have involved a four-lane bridge being built closer to the existing Britannia Bridge than the chosen purple option, and having a much lower deck, to protect views of the existing bridge. A "Three Bridges Park" development was then proposed alongside the third crossing proposal in the hope the three bridges would become a tourist attraction and provide "wider economic benefits". However, there was no indication the proposal was seriously considered by the Welsh Government before it scrapped the crossing project entirely.[2]

Design and cost

Four bridge types were considered during the 2017 public consultation. The four types considered were: a single-span extrados, two-span extrados, two-span balanced cantilever or a single-span cable-stayed bridge.[40] The balanced cantilever design was most favoured by respondents due to its low profile.[11]

A local civil engineer, disagreed that the new bridge should have a low profile, stating it "looked a bit more like a motorway overpass", so instead put forward a proposal for the bridge to be held up by a statue of Bendigeidfran, a Welsh mythological figure. The concept won a design competition, with a petition for it later launched, receiving near 300 signatures. The Welsh Government included the concept in its appraisal process to its project consultants.[11][41]

The bridge was proposed to have wind protection to avoid the bridge being closed to road traffic under stormy conditions.[8]

The bridge would be fully funded by the Welsh Government, as of 2022.[26] Although it was hoped in 2017, that the National Grid would provide funds for the project in the event their cables are carried along the new bridge instead of their own proposed £100 million tunnel under the strait connecting to the proposed Wylfa Newydd nuclear power station. A tunnel was proposed by the National Grid instead of electricity pylons to protect the area's natural beauty.[8][42] Llyr Gruffydd, Plaid Cymru MS, said the combined project would make a crossing "more feasible". A 2018 National Grid and Welsh Government study was set up to investigate the proposal.[43]

The crossing was estimated to cost £135 million in 2017,[7] but increased to £400 million by 2022.[24][44] Design consultants for the crossing were stated to be AECOM, RML and Knight Architects.[10][39][45][46][47]

Criticism

The justification for a crossing was stated to be weaker following a decrease in the predicted traffic forecasts across the strait, due to the impact of Brexit on the Port of Holyhead and the shelving of the planned Wylfa Newydd nuclear power station.[11]

Criticism was also directed towards the managing of the proposal.

On slowed progress

Slow progress with the project has come under criticism for the Welsh Government.

Russell George Conservative MS, had criticised the slow progress of the project, which George said was "long overdue". George stated that the project had been in the works for "more than a decade [...] yet the Welsh Government have done nothing".[9] Mark Isherwood, Conservative MS also criticised the slow progress following the announcement that the project would be reviewed in June 2021.[48] Lee Waters, Deputy Minister for Climate Change stated "all schemes not currently in the ground need to be reviewed" and the congestion "can be dealt with in other ways" such as more road maintenance and improved public transport.[49]

Rhun ap Iorwerth, Plaid Cymru MS, called on the government to "act quickly" following the temporary Menai Bridge closure in late 2022. Lee Waters responded stating the project would not be a solution in the near future and would require a lot of consideration in particular over the £400 million cost, and that alternative shorter-term arrangements without a bridge were also being considered.[27]

The Welsh Conservatives accused the government of failing to fix a known defect on the Menai Bridge for 20 years, causing its temporary closure, and called for the third crossing proposal to be "accelerated given the new bridge will take seven years to build".[50]

On scrapping and alternatives

On 14 February 2023, the project was announced it would not go ahead, as part of the Welsh Government roads review, over concerns of increasing car usage and therefore carbon emissions.[1]

Rhun ap Iorwerth, Plaid Cymru MS, described the scrapping as an "insult" to the people of Anglesey, with the project being described as "desperately needed",[51] and later stated it would be needed to address the existing "extremely weak crossing [over the Menai Strait] [...] that needs strengthening for the long term".[4][5] He also stated that alternative plans instead of a third crossing had become contradictory.[2] Ap Iorwerth highlighted that the Welsh Government hopes to double the rail line on the Britannia Bridge, which it is currently single track. While at the same time increase pedestrian and cyclist links across the strait, which currently utilises the empty space on the Britannia Bridge where another rail track would be.[2]

Virginia Crosbie, Conservative MP for Ynys Môn, criticised the recommended scrapping stated it "lack[ed] common sense" and would "systematically destroy the Welsh economy". Crosbie argued the crossing should be considered as "our roads are getting greener", providing the use of electric vehicles as an example.[51]

Ken Skates, Labour MS and former transport minister, called for devolution of transport to North Wales, over the scrapping of the majority of North Wales' road projects.[32][52]

See also

References

  1. 1 2 3 4 Forgrave, Andrew (14 February 2023). "Third Menai crossing and 'Red Route' axed as major road-building plans scrapped". North Wales Live. Retrieved 14 February 2023.
  2. 1 2 3 4 5 6 7 Forgrave, Andrew (6 February 2023). "New 'Sienna' route and tourism park proposed for Third Menai Crossing before scheme was axed". Daily Post. Retrieved 16 February 2023.
  3. "Plans for third Menai crossing axed in review of road improvements in Wales". North Wales Chronicle. Retrieved 17 February 2023.
  4. 1 2 3 "No money for major road projects in Wales, minister says". BBC News. 19 February 2023. Retrieved 19 February 2023.
  5. 1 2 3 Lennox, Aaran (19 February 2023). "Welsh Government could 'look again' at third Menai crossing". North Wales Live. Retrieved 19 February 2023.
  6. 1 2 3 4 "Preferred third Menai crossing announced by first minister". BBC News. 11 October 2018. Retrieved 25 May 2022.
  7. 1 2 3 "Menai Strait £135m third crossing plans outlined". BBC News. 15 December 2017. Retrieved 15 January 2023.
  8. 1 2 3 4 5 "Third Menai Strait bridge 'could be built by 2021'". BBC News. 5 October 2017. Retrieved 25 May 2022.
  9. 1 2 3 4 "Third Menai crossing construction 'could start by 2021'". BBC News. 11 August 2016. Retrieved 25 May 2022.
  10. 1 2 3 4 "A55: 3rd Menai Crossing (overview)". GOV.WALES. Retrieved 15 January 2023.
  11. 1 2 3 4 5 6 7 8 9 10 Forgrave, Andrew (29 October 2022). "Third Menai bridge reaches critical crossroad after two decades of debate". North Wales Live. Retrieved 19 February 2023.
  12. 1 2 Options Under Consideration (PDF). Welsh Government. 1 July 2017.
  13. 1 2 Options for Crossing the Menai Strait (PDF). Welsh Government. 1 July 2017.
  14. Objectives: Why are we looking at the A55 3rd Menai Crossing? (PDF). Welsh Government. 1 July 2017.
  15. "Wylfa B transport plan suggests third Menai bridge". BBC News. 26 September 2011. Retrieved 15 January 2023.
  16. Hughes, Owen (15 November 2019). "Menai Strait £130m bridge project under threat after nuclear plant suspension". Business Live. Retrieved 17 February 2023.
  17. "New Menai bridge to be considered". BBC News. 4 February 2013. Retrieved 15 January 2023.
  18. "Plaid and the Welsh Government have agreed a £210m deal ahead of the draft budget". ITV News. 1 October 2017.
  19. 1 2 "A55 3rd Menai Crossing: preferred route". GOV.WALES. Retrieved 15 January 2023.
  20. Hughes, Owen (10 February 2022). "The list of 55 road schemes under review in Wales by climate change panel". Business Live. Retrieved 15 January 2023.
  21. "Welsh Government freezes new road projects". Place North West. 23 June 2021. Retrieved 15 January 2023.
  22. Hughes, Owen (22 June 2021). "Welsh Government presses pause on building new roads in Wales". Business Live. Retrieved 16 January 2023.
  23. Johnson, Thomas (7 December 2022). "Funding uncertainty delays 55 north Wales road projects including third Menai crossing". New Civil Engineer. Retrieved 15 January 2023.
  24. 1 2 "Menai bridge: Third crossing by 2030 likely - Welsh government". BBC News. 14 December 2022. Retrieved 15 January 2023.
  25. Hughes, Owen (14 December 2022). "Third Menai crossing could start getting built by 2027 according to Welsh Government's project pipeline". North Wales Live. Retrieved 15 January 2023.
  26. 1 2 "Third Menai crossing on cards for 2027 start". Place North West. 14 December 2022. Retrieved 15 January 2023.
  27. 1 2 3 "New Anglesey crossing would cost £400m and take seven years to build says minister after Menai Bridge closure". Nation.Cymru. 25 October 2022. Retrieved 15 January 2023.
  28. Hughes, Owen; Jones, Branwen (14 December 2022). "Third Menai crossing in Welsh Government's project pipeline". WalesOnline. Retrieved 15 January 2023.
  29. Hatmaker, Julia (15 February 2023). "Govt ditches major North Wales roadwork projects". Place North West. Retrieved 17 February 2023.
  30. 1 2 The Future of Road Investment in Wales (PDF). Welsh Government. 2023.
  31. 1 2 Aye, The Bangor (14 February 2023). "Plans for third Menai crossing dropped by Welsh Government". The Bangor Aye. Retrieved 17 February 2023.
  32. 1 2 "Third Menai crossing scrapped along with A55 and A483 road schemes as Welsh Government publishes review". North.Wales. Retrieved 17 February 2023.
  33. Morris, Steven (14 February 2023). "Welsh road building projects stopped after failing climate review". The Guardian. ISSN 0261-3077. Retrieved 17 February 2023.
  34. Mansfield, Mark (22 September 2023). "Cross-party group steps up campaign for third Menai crossing". Nation.Cymru. Retrieved 28 December 2023.
  35. 1 2 Bevan, Gareth (2 November 2023). "Petition launched calling for the third Menai crossing to be built". Herald.Wales. Retrieved 28 December 2023.
  36. "Petition launched calling for a third Menai crossing to be built on Ynys Môn". North Wales Chronicle. 1 November 2023. Retrieved 28 December 2023.
  37. Hughes, Owen (14 December 2023). "Lower speeds, wind deflectors and speed cameras recommended for Menai bridges". North Wales Live. Retrieved 28 December 2023.
  38. Environmental Constraints (PDF). Welsh Government. 1 July 2017.
  39. 1 2 "£135m Third Menai Crossing route selected". Construction Enquirer. Retrieved 16 January 2023.
  40. Bridge Types (PDF). Welsh Government. 1 July 2017.
  41. Jones, Mari (19 December 2018). "Plans for giant mythical king to hold up Menai crossing take a step forward". North Wales Live. Retrieved 19 February 2023.
  42. "Wylfa Newydd: Power tunnel under Menai Strait to cost £100m". BBC News. 30 September 2016. Retrieved 15 January 2023.
  43. "Third Menai crossing study to look at adding power cables". BBC News. 6 May 2018. Retrieved 15 January 2023.
  44. Moore, Catherine (28 October 2022). "Third Menai crossing costs treble to around £400M". New Civil Engineer. Retrieved 15 January 2023.
  45. Hopkirk, Elizabeth (2 May 2017). "Knight to design third bridge across Menai Strait". Building Design. Retrieved 16 January 2023.
  46. Waite, Richard (2 May 2017). "Knight Architects to design third Menai bridge". The Architects’ Journal. Retrieved 16 January 2023.
  47. Schouten, Charlie (27 April 2017). "Aecom wins design deal for new Menai bridge". Construction News. Retrieved 16 January 2023.
  48. "Welsh Government challenged over promised third Menai crossing following freeze on new road projects". North.Wales. Retrieved 15 January 2023.
  49. "MS calls for update on proposals to build third bridge to Anglesey". North Wales Chronicle. Retrieved 15 January 2023.
  50. "Welsh Government slammed for '20 years of inaction' after cause of Menai Bridge closure revealed". Deeside.com. Retrieved 16 January 2023.
  51. 1 2 "Anglesey: Plans to axe new bridge an 'insult' to locals". BBC News. 15 February 2023. Retrieved 17 February 2023.
  52. Evans, Matthew (15 February 2023). "Residents will think 'Cardiff is as remote as Westminster' as roads plans axed". North Wales Live. Retrieved 17 February 2023.

53°13′00″N 4°11′01″W / 53.2168°N 4.1837°W / 53.2168; -4.1837

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.